The existing roof membrane required replacement and the concrete slab beneath required repair before a new telecommunications tower could be installed. The waterproofing scope also had to be coordinated with the electrical crew working in the same roof plant area.
Waterseal coordinated with the electrical crew, replaced the existing roof membrane and completed the required concrete slab repairs within the roof plant area ahead of the planned telecommunications tower installation.
Site photography showing existing conditions, preparation, installation and completed detailing.
The documented membrane-replacement and slab-repair scope was completed, preparing the roof plant area for the planned telecommunications tower installation.